Summary of LASCO/EIT Recommissioning Steps
Recommissioning began Tuesday October 13 at 1:00 PM EST (17:00 UT)
EIT images have been successfully taken in all four wavelengths.
C3 Coronal images have been taken and appear fine.
C2 Coronal images have been taken and appear fine.
Update - Wednesday October 15th: The C2 door has been opened and C2 coronal images have been taken.
See latest images here
(note: the C3 images have not had the f-corona/stray-light
model subtracted because the spacecraft is rolled ~53 degrees. It will probably be
rotated back on Friday to put solar north up.)
A more
detailed status report is availaible as a separate file from the normal status reports.
This is a summary of the steps that will be followed during the recommissioning of the
LASCO and EIT instruments. A check mark will appear when the steps are completed along
with the date and time of completion. After Block 2, the blocks could be performed in a
different order than what appears here.
Block 1
Boot all processors, turn on thermal control, check proper interprocess communications
-
13/17:00 UT
Verify non-operational temperatures are within operational limits
-
13/17:33 UT
TSTOL Procedure to power the LEB, inhibit automatic boot using NRT
-
13/17:49 UT
Configure relays for normal operations on the A-side
-
13/17:49 UT
Check out TCE HK monitors
-
13/17:56 UT
Turn experiment power on
-
13/18:01 UT
Boot instrument controller board
-
13/18:05 UT
Check out ICE HK functions/mechanism status
-
13/18:05 UT
Turn on LASCO/EIT zone heaters
-
13/18:31 UT
Manually boot OBE (main processor)
-
13/18:35 UT
Check out OBE operation
-
13/18:44 UT
Turn PROM card power off
-
Manually boot each camera and FP processor in succession, checking monitors
- 13/18:57 UT - C1 - OK
- 13/18:59 UT - C2 - OK
- 13/18:02 UT - C3 - OK
- 13/18:04 UT - EIT - OK
- 13/18:13 UT - FP - running from RAM (still checking monitors)
-
Take 0 and 60 second dark images from each camera (8 images)
- 13/19:22 UT - C1 - 0 sec - OK
- 13/19:33 UT - C2 - 0 sec - OK
- 13/19:50 UT - C3 - 0 sec - OK
- 13/19:56 UT - EIT - 0 sec - OK
- 13/20:09 UT - EIT - 60 sec - OK
- 13/20:26 UT - C3 - 60 sec - OK
- 13/23:30 UT - C2 - 60 sec - OK
- 13/23:40 UT - C1 - 60 sec - OK
Block 2
Check EIT mechanisms and camera, Image XUV Corona, Check C2/C3 mechanisms, camera
-
13/20:42 UT
Check out EIT calibration lamp
-
13/20:44 UT
Take an EIT calibration lamp image
-
13/20:55 UT
Check out EIT shutter
-
13/20:58 UT !!!
Take a solar EIT image in current filter/sector. 195A Image looks perfect!!
-
13/21:55 UT
Checkout EIT camera
-
13/21:55 UT
Check out EIT sector wheel
-
13/21:55 UT
Take EIT solar images in each sector
-
13/23:00 UT
Check out EIT CCD heaters
-
13/23:55 UT
Check out C1, C2 and C3 cal lamps and shutters
-
14/00:45 UT
Checkout C2 filter wheel, polarizer wheel
-
14/18:01 UT
Check out EIT filter wheel
-
14/18:20 UT
Checkout C3 filter wheel, polarizer wheel
-
14/18:38 UT
Checkout C3 camera
-
15/14:00 UT
Checkout C2 camera
Block 3
Open C3 Door, First Light Image of C3 Corona
-
14/18:35 UT - Cal Lamp check - OK
-
14/18:58 UT - Calibration Window Check -
Orange/Clear - OK
-
14/19:12 UT -
Adjust COB legs as necessary. Deleted: Not necessary
-
14/19:12 UT -
Opened C3 Door
-
14/19:20 UT -
Check COB Pointing
-
14/19:17 UT - C3 H-alpha/Clear - OK
-
14/19:20 UT - C3 Clear/Clear - OK
-
Dark image checks: 0, 60, 300 seconds
15/22:18 UT - C3 0 Sec - OK
15/22:43 UT - C3 60 Sec - OK
15/23:29 UT - C3 300 Sec - OK
Block 4
Open C2 Door, First Light Image of C2 Corona
-
Calibration Lamp Checks
-
15/20:00 UT -
Open C2 Door
15/20:15 UT -
C2 alignment and pointing test using H-alpha filter
- Adjust COB legs if necessary SKIPPED
- Adjust IOCS if necessary SKIPPED
-
15/20:17 UT -
C2 First Light Image Orange/Clear - OK
-
Dark image checks: 0, 60, 300 seconds
15/22:11 UT - C2 0 Sec - OK
15/22:35 UT - C2 60 Sec - OK
15/23:02 UT - C2 300 Sec - OK
Block 5
Door Closed Calibration of C3
-
17-18 October -
Cal lamp images of all filter and polarizer combinations (21 images)
-
18-19 October - Repeated
-
19-20 October - Repeated
-
17-18 October -
Image calibration window through all filters and polarizer combinations (21 images)
-
18-19 October - Repeated
-
19-20 October - Repeated
Block 6
Door Closed Calibration of C2
-
17-18 October -
Cal lamp images of all filter and polarizer combinations (13 images)
-
18-19 October - Repeated
-
19-20 October - Repeated
-
17-18 October -
Image calibration window through all filters and polarizer combinations (10 images)
-
18-19 October - Repeated
-
19-20 October - Repeated
-
Door Cal Lamp Image with Lens/Clear
Block 7
EIT Calibration
-
19-20 October -
Full calibration of EIT telescope
Block 8
Check out C1 mechanisms, camera and Fabry-Perot
-
Checkout C1 mechanism
-
Checkout C1 camera
-
Checkout Fabry-Perot
-
14 October -
Set PZT voltages to zero in reduced capability mode
-
19 October -
Step PZT voltages in reduced capability mode through entire range
-
Set CLR/Z offset/Y offset/X offset/Range DACS to nominal settings
-
Enter Servo Mode
-
Command Range DAC through its range in servo mode
-
Cycle FP Launch Lock - Skipped
- Image Door Calibration Window in all Filter Combinations/ Clear Polarizer (5 images)
Block 9
Re-open C2/C3 Doors, calibration checks of C2/C3
-
Open C3 Door
-
Exposure time checks in all C3 filter and polarizer combinations (21 images)
-
Repeat
- Photon Transfer Curve images through all C3 filters (4 images)
-
Open C2 Door
-
15 Oct 98 -
Image C2 with Lens, ND filter to show fringe pattern
- Move IOCS if necessary - Skipped
- Adjust COB legs if necessary - Skipped
- Adjust IOCS if necessary - Skipped
-
Exposure time checks in all C2 filter and polarizer combinations (21 images)
-
Repeat
- Photon Transfer Curve images through all C2 filters (3 images)
- Adjust COB legs if necessary - Skipped
- Adjust IOCS if necessary - Skipped
- Adjust Focus if necessary - Skipped